Computer Science Fundamentals Software Engineering Objective
May 20, 2013

Requirements Specification, Planning, Test case Design, Execution,Bug Reporting & Maintenance This Life Cycle comes Under

Choose the correct answer:
A) SDLC
B) STLC
C) SQLC
D) BLC
Detailed Explanation

Option b is right answer.

Discussion (0)